Evidence From Complex Delivery, Governance and Risk
Selected examples of how I have approached complex constraints, strengthened governance and translated performance information into practical decisions.
Project Delivery & Logistics
Farasan Island RO Plant
Managing a remote-island desalination project where ferry capacity, imported equipment and multiple contractors created a critical delivery constraint.
Approx. SAR 90M
project value
Approx. 250-person
workforce
Completed in about 9 months
against a 12-month plan
Secured three weekly ferry trips, aligned suppliers and contractors, and used off-site fabrication and preassembly to protect delivery.
King Abdulaziz International Airport Power Facility
Leading multidisciplinary MEP delivery for a mission-critical 70.4 MW emergency power-generation facility, from installation and testing through client acceptance and handover.
16 medium-voltage generators | Approx. SAR 45M MEP scope | Approx. SAR 1M sourcing savings
Supporting the development and launch of a major entertainment destination through stakeholder coordination, contractor performance, commercial governance and PMO visibility.
Approx. three months and one week to completion | Six main contractors | 600+ purchase orders | Approx. SAR 900M commercial closeout